According to a notice from partner Viettel Hoa Lac, vHost would like to update information about power infrastructure schedule at datacenter Viettel Hoa Lac, specifically as follows:

 

  • Start time: February 26, 2024 23:00 (GMT+7).
  • End time: February 27, 2024 04:00 (GMT+7).
  • Reason: Power infrastructure maintenance partner.
  • Impact: None

 

Note: the above time is planned time, the actual maintenance time may be done sooner.