Scheduled on 21/10/2026 21:00:00 Estimated finish 24/10/2026 04:00:00

Dear Valued Customers,

Thank you for trusting and using services at vHost over the past time.

To ensure stable system operation and improve service quality, vHost would like to respectfully announce the maintenance plan with detailed information as follows:


  • Maintenance content: FPT storage cluster maintenance.

  • Phase 1:
  • Start time: 21:00 on 21/10/2026 (GMT +7:00 – Vietnam Time Zone).

  • End time: 04:00 on 22/10/2026 (GMT +7:00 – Vietnam Time Zone).

  • Phase 2:
  • Start time: 21:00 on 23/10/2026 (GMT +7:00 – Vietnam Time Zone).

  • End time: 04:00 on 24/10/2026 (GMT +7:00 – Vietnam Time Zone).

  • Impact: No service interruption. However, latency will occasionally increase during the maintenance period.

Note: The above schedule is estimated. Due to the large volume of data, rebalancing data across the new drive system will take a considerable amount of time. We kindly ask for your understanding and support.

In case you need further assistance, please contact vHost via the following channels:

Call Center: 1900 6806 – press 2 (Technical Department)
Email: support@vhost.vn

Best regards,

Service: Services at FPT Data Center in Ho Chi Minh City

Scheduled on 21/10/2026 21:00:00 Estimated finish 24/10/2026 04:00:00

Dear Valued Customers,

Thank you for trusting and using services at vHost over the past time.

To ensure stable system operation and improve service quality, vHost would like to respectfully announce the maintenance plan with detailed information as follows:


  • Maintenance content: FPT storage cluster maintenance.

  • Phase 1:
  • Start time: 21:00 on 21/10/2026 (GMT +7:00 – Vietnam Time Zone).

  • End time: 04:00 on 22/10/2026 (GMT +7:00 – Vietnam Time Zone).

  • Phase 2:
  • Start time: 21:00 on 23/10/2026 (GMT +7:00 – Vietnam Time Zone).

  • End time: 04:00 on 24/10/2026 (GMT +7:00 – Vietnam Time Zone).

  • Impact: No service interruption. However, latency will occasionally increase during the maintenance period.

Note: The above schedule is estimated. Due to the large volume of data, rebalancing data across the new drive system will take a considerable amount of time. We kindly ask for your understanding and support.

In case you need further assistance, please contact vHost via the following channels:

Call Center: 1900 6806 – press 2 (Technical Department)
Email: support@vhost.vn

Best regards,

Service: Services at FPT Data Center in Ho Chi Minh City

Scheduled on 16/09/2026 22:00:00 Estimated finish 17/09/2026 06:00:00

Dear Valued Customer,

Thank you for trusting and using the services at vHost throughout this time.

In order to ensure stable system operation and improve service quality, vHost would like to respectfully announce the following maintenance plan:


  • Maintenance content: Upgrading the Proxmox system to the latest PVE version.

  • Start time: 22:00 on 16/09/2026 (GMT +7:00 – Vietnam time zone).

  • End time: 06:00 on 17/09/2026 (GMT +7:00 – Vietnam time zone).

  • Impact: Each VM will be rebooted once, causing a brief interruption of approximately 3-10 minutes during the maintenance period.



Note: The reboot will be performed by vHost's engineers. Should you reboot your VPS/Cloud Server manually, this will not prevent our system from rebooting it again during the maintenance window. We appreciate your understanding and cooperation.

Should you require further assistance, please contact vHost through the following channels:

Call Center: 1900 6806 – press 2 (Technical Department)
Email: support@vhost.vn

Best regards,

Services: Services at Viettel Ha Noi Datacenter