Scheduled on 29/01/2026 00:00:00 Estimated finish 29/01/2026 00:30:00


  • Maintenance Scope: Firmware upgrade for the router devices at the FPT DataCenter.

  • General Impact: Traffic will reroute to another router during maintenance. The maximum network disruption duration is up to 5 minutes.

Scheduled on 24/01/2026 22:00:00 Estimated finish 25/01/2026 06:00:00


  • General Impact: All services hosted at the Viettel Binh Duong Datacenter will not be accessible during the maintenance period.

  • Detailed Service Impact:

    • Cloud Server,VPS: Virtual Machines will be shut down.

    • Email Server, Email Pro, Email Hosting, Email Relay: Access to the email system and mail delivery (sending/receiving) will be temporarily interrupted. Incoming emails will be held in the Mail Gateway queue and delivered immediately after maintenance.

    • vDrive System: The system will be temporarily unavailable.

    • Kubernetes: The management dashboard and API connectivity will be temporarily disrupted. Running workloads on existing clusters will not be affected.

    • Hosting: Websites will be temporarily offline.

    • Bare Metal Server: Servers will be shut down.


Service Impact: Hosting, Email, Cloud Server, VPS, Bare Metal Server, vDrive, Kubernetes.

Scheduled on 19/01/2026 17:14:00 Estimated finish 19/01/2026 17:15:00


  • Root Cause: The routing device was rebooted due to a software issue.

  • Detailed Service Impact: The FPT networks were temporarily disrupted at that time.

  • Current Status:

    The network is now operating normally, and vHost will plan maintenance to prevent a recurrence of this issue.


Service Impact: Hosting, Email, Cloud Server,...